Roadway & Lot Paving

 
CVE_MasterManagement221.jpg
MM.png

Master Management has a multi-year paving plan that will resurface all major roadways throughout the village.

 
 

GENERAL 2018 PAVING INFO

Master Management's 2018 paving plan includes the following area: Prescott (not A, B, C, D, & E), Tilford, Ventnor, Ellesmere.  Each area will be done individually according to a schedule.  See below for more information.

Vehicles must be removed from their parking spaces no later than 8:00AM the day your building is scheduled to be paved and cannot be returned to their parking spaces until the following day. Parking is available at the Clubhouse, if needed (first lot to the right as you enter off of Century Blvd.).

Residents planning to be away during this time and leaving a vehicle at their Association should make arrangements to leave keys with a resident who resides on the property full-time so their vehicle can be moved during the paving process. Please advise Ray DePerro of Five Star Sealing and Paving at (954) 650-2347 the name, unit number, and telephone number of the individual that will have your keys. If your vehicle is in a parking space when paving begins, it is likely to be towed by your Association at your own expense.

WEATHER DELAYS:   Please note that rain will create delays in the paving.  If the exact dates change a bit due to weather delays, please be patient.

UPDATES BELOW. MOST RECENT IS FIRST

 
 

UPDATED THURSDAY, AUG 30

Paving will continue for the remainder of the Prescott areas the week of September 3rd. This will complete the 2018 Paving Project.

 

Monday, September 3rd

  • No Paving due to Labor Day Holiday

Tuesday, September 4th

  • Remainder of Prescott K

  • Prescott L - Roadway & Parking Spaces

Wednesday, September 5th

  • Tilford Drive - Including Prescott O Parking Spaces

Thursday, September 6th

  • Prescott N - Roadway & Parking Spaces

Friday, September 7th

  • Prescott M - Roadway & Parking Spaces


UPDATED FRIDAY, AUG 24

Due to the elections on Tuesday, August 28th, the paving schedule is being revised as follows:

Monday, August 27th

  • Tilford X & S - Roadway & Parking Spaces

Tuesday, August 28th

  • Prescott F - Roadway and Parking Spaces

Wednesday, August 29th

  • Prescott G - Roadway & Parking Spaces

  • Prescott H - Roadway and Parking Spaces up to Parking Space #163

Thursday, August 30th

  • Remainder of Prescott H - Roadway and Parking Spaces

  • Prescott I - Roadway and Parking Spaces

 Friday, August 31st

  • Prescott J - Roadway and Parking Spaces

  • Prescot K - Roadway and Parking Spaces up to Parking Space #20

Note: There will be no Paving on Monday, September 3rd, Labor Day

Paving Schedules for the remainder of the Prescott areas will be Posted the week of September 3.


UPDATED WEDNESDAY, AUG 1

Paving will continue the week of August 6th as follows:

  • Tilford G & H Parking Spaces & South Side Roadway - Monday, August 6th 

  • Tilford E & F Parking Spaces & North Side Roadway - Tuesday, August 7th

  • Tilford D Parking Spaces & North Side Roadway - Wednesday, August 8th

  • Tilford D, E & H Parking Spaces & West Side Roadway - Thursday, August 9th

  • Tilford J Parking Spaces & Roadway - Friday, August 10th

  • Dates for the Paving of additional Tilford areas will be posted the week of August 13th

  • Paving Schedules for further Tilford areas, as well as the Prescott area will follow in the near future.


UPDATED MONDAY, JULY 31

We will begin paving of the Tilford area roadways and association parking beginning the week of 7/30/18.


UPDATED WEDNESDAY, JULY 18

Paving for the Ventnor area will continue as follows:

  • Ventnor O Roadway and Parking Spaces up to Parking Spot # 4054 - Monday, July 23rd

  • Remainder of Ventnor O Roadway and Parking Spaces up to Ventnor P - Tuesday, July 24th

  • Ventnor P Roadway and Parking Spaces up to Parking Spot # 2066 - Wednesday, July 25th

  • Remainder of Ventnor P Roadway and Parking Spaces, including Roadway up to Ventnor S Entrance - Thursday, July 26th and Friday, July 27th

  • Dates for Paving the Remainder of the Ventnor S area, as well as Tilford A, B, and C will be posted the week of July 23rd

  • Paving Schedules for the remaining Tilford and Prescott areas will follow in the near future.

All scheduled paving is dependent upon current weather conditions and any potential unforeseen issues. Additional details are posted at each building. Please note there will be traffic detours during the paving process, if necessary. Security will assist with the redirection of traffic, as needed, during these times.

 


UPDATED THURSDAY, JULY 12

Paving for the Ventnor area will continue west from Ventnor Drive and the Ventnor H Building:

  • Ventnor H Roadway and Parking Spaces up to Parking Spot # 3025 - Monday, July 16th (This includes Ventnor F, east Parking Spaces, opposite Ventnor H Building)

  • The remainder of Ventnor H Roadway and Parking Spaces to end of the roadway - Tuesday, July 17th

  • Ventnor F and Ventnor G Roadway and Parking Spaces up to the Entrance of Ventnor E - Wednesday, July 18th

  • Ventnor E Roadway and Parking Spaces - Thursday, July 19th

  • The remainder of Ventnor G Roadway and Parking Spaces up to Ventnor O - Friday, July 20th

  • Dates for Paving of the Ventnor O, P, and S areas will be announced the week of July 16th

  • When Ventnor area Paving is complete, the Paving Schedule for Tilford A, B, and C areas will be posted

  • Paving Schedules for the remaining Tilford and Prescott areas will follow in the near future

All scheduled paving is dependent upon current weather conditions and any potential unforeseen issues.  Additional details are posted at each building.

 

Please note there will be traffic detours during the paving process, if necessary.  Security will assist with the redirection of traffic, as needed, during these times.

 

Vehicles must be removed from their parking spaces no later than 8:00AM the day your building is scheduled to be paved and cannot be returned to their parking spaces until the following day.  Parking is available at the Clubhouse, if needed (first lot to the right as you enter off of Century Blvd.)

 

Residents planning to be away during this time and leaving a vehicle at their Association should make arrangements to leave keys with a resident who resides on the property full-time so their vehicle can be moved during the paving process.  Please advise Ray DePerro of Five Star Sealing and Paving at (954) 650-2347 the name, unit number, and telephone number of the individual that will have your keys.  If your vehicle is in a parking space when paving begins, it is likely to be towed by your Association at your own expense.

 


UPDATED THURSDAY, JUNE 28:

Please note the following REVISIONS to the Ventnor area paving:

Ventnor C Roadway and Parking Spaces on Friday, June 29thVentnor D & I Roadway and Parking Spaces on Monday, July 2ndVentnor J Roadway and Parking Spaces on Tuesday, July 3rd

THERE WILL BE NO PAVING TAKING PLACE ON WEDNESDAY, JULY 4TH, THURSDAY, JULY 5TH, AND FRIDAY, JULY 6TH

Ventnor K Roadway and Parking Spaces on Monday, July 9thVentnor L Roadway and Parking Spaces on Tuesday, July 10thVentnor Q Roadway and Parking Spaces on Wednesday, July 11thVentnor M Roadway and Parking Spaces on Thursday, July 12thVentnor R Roadway and Parking Spaces on Friday, July 13th

 

All scheduled paving is dependent upon current weather conditions and any potential unforeseen issues. Additional details will be posted at the Ventor C building.

 



EARLIER PHASES:

The first portion of the village paving is underway.  The map below indicates the locations of the first phase which will take place in June.  They include Prescott F, G, H, H, I, J, K, L, & M.

prescott paving.png
 

FUTURE PHASES

The future phases will include Tilford, Ventnor, and Ellesmere.  As soon as definite dates are set for these sections, they will be posted here.